|

Excerpts from the Transcript of Coastal Commission Hearing on Noyo
Bridge Appeal and Application
Friday, March 12, 1999
Excerpts made by Vince
Taylor
The emphasis and comments in "[]" brackets are mine.
The excerpts demonstrate several points:
- In discussing what made railings acceptable to it, Caltrans only cited the need to meet
current safety standards, nothing more. Several of the remarks make the inference that
federal crash-testing standards are what determine the acceptability of railings.
- The staff repeatedly asserts that Caltrans told them that any changes in railing design
or bridge width would lead to unacceptable delays that would kill the project.
- The staff asserts that because no changes were acceptable to Caltrans, the only way to
meet the requirements of preserving coastal visual resources was to impose "Condition
No. 6," a $2 million mitigation fee (reduced to $1 million by the Commission).
| Jack Liebster, staff No
changes or redesign were acceptable to Caltrans |
p. 18. Now, one of
the things that we looked at was what kind of alternatives would be available to avoid the
impacts from the proposed design of the bridge. But, basically, anything that we really
could suggest, in terms of physical changes, was not considered acceptable by Caltrans,
for the simple fact that it would delay the construction of the bridge. p. 19. We also
looked at the impact or the possibility of a narrowed design of the bridge, but
underlying all of these suggestions, or alternatives, was the simple fact that all of
these would require some change in the existing plans, and also most likely a lot of
study, and exceptions to the present approval, or actual changes in the present Caltrans
guidelines that could not be accomplished within the timing that Caltrans preferred for
this project. |
| Rick Knapp, Caltrans Critical
seismic safety project.
Quickly as possible.
Underway by July of 99.
Cant afford any further delays
Negative declaration approved. [?]
Safety standards for bridge railings
Must build railings that meet safety standards
Golden Gate doesnt meet current standards.
Difficulty of getting CTC approval for extra funding |
p. 23. This is a
critically important seismic safety project. It is one of only 27 of the 1155 safety
seismic projects that are left to be built in the state. We have a legislative mandate. We
were required to be done with all of the retrofits by December of 97, so we are down
to the real tough ones
.
It must be replaced as quickly as possible. We are
done with the environmental process, with the design process, with the public phase of the
project, and we are down to the acquisition of the final permits, this one, and the permit
from the Coast Guard, and then we will have this project underway in July of '99.
We cant afford any further delays if we are going to get this project underway
this season. We have short work windows, due to the Cojo, and other environmental
constraints on the project, and we cant work past October 15 in the stream. We are
now in the 5th month of our effort to get the coastal permits for this project.
This project has a negative declaration, and finding of no significant impact both
approved by Caltrans and FHWA, Federal Highway Administration.
We have included the first ever see-through bridge railing in response to concerns
expressed by the public. [This is quite a statement what about all the older
bridges that have wonderful, visually transparent railings?] While it does not provide the
visibility as you saw of the existing railing, the existing railing does not meet safety
standards, and for an agency that pays over $50 million a year in torte liability, we
dont go out and build railings that dont meet safety standards. We cannot do
it. We would be paying many, many, many millions more.
The other railings that Mr. Liebster showed you do not meet current standards. The
Golden Gate Bridge does not meet current standards, and if it were built today it would be
150-feet wide. Now, it is important and the Bay Bridge will be somewhere in the
175-feet wide. So, you know, looking at bridges that were build 75 years ago isnt,
you know, is not the standard we use to determine what we should build today.
[The Golden Gate Bridge could almost certainly meet current standards, having a
42" high, smooth steel barrier rising from the roadway, backed by the sidewalk at
27" in height. The fact that no vehicle has surmounted this traffic barrier in 50
years suggests how successful is the design. Because current standards require crash
testing, it would be necessary to build a section of the railing and test it to gain
formal acceptance something not likely to happen, but which doesnt change the
reality of the safety of its design.]
We have already exceeded the cost that was programmed for this project by 20 percent.
That is the maximum we can go. We will have to go back to the California Transportation
Commission. If we dont get the money you know, if we need additional money
for conditions, and I cant tell you what the fate of the project will be. It is
very, very difficult to go back and get additional money. [Ha! The Commissioners of
the CTC were chomping at the bit to approve funding at their June meeting, in spite of my
testimony showing how a better design would save $4.5 million.]]
|
| Karen Tatman,
Caltrans Cost of new railing high because it has never been built |
p. 38
Standard
railing would only cost about $200,000 -- $250,000 on this bridge, and by standard railing
I mean the solid concrete, what we term as Type 26 railing. The additional cost to build
this see-through railing is another $220,000, so the cost of providing or the
see-through railing is consisting over and above by $220,000, about that cost. It is
important to point out that because the see-through railing has never been built before,
the contractors dont have the forms.
This rail has never been built before, so
the forms arent readily available, so a contractor is going to have to create those
forms. That is what makes it so much more expensive. |
| Mark Massara 2
years to develop new rail |
p. 61. More
importantly, even better view protecting rails can and are being developed. Caltrans says
it will take approximately 2 years to invent better rails. You have compelling incentive
to force this issue now, that being the dozens of coastal bridge projects that will come
before you over the next decade. |
| Rick Knapp Safety
standards need to meet those for federally supported highways |
p. 75. I would be
happy to respond to any other comments that were raised that challenged things that
Caltrans has done. One would be, I guess, the see-through railing. Certainly, there are
numerous see-through railings. They dont meet standards. And, we dont get to
set standards in Fort Bragg, you know, for national highways, federally supported
highways. We go through rigorous testing of railings, and we were able to be successful in
accelerating that testing process, in order to the first see-through safety railing
approved. [Again note the only qualification is "rigorous testing" to
get approval.]
[Note also that there was no argument with 2-years to develop railing.]
As was pointed out by your last speaker
[interruption] there are lots of solid
ones that are being built. And, that is why, because we didnt have an approved
safety one. [ Again, "safety one"] |
| Peter Douglas, Exec.
Director Caltrans asserted that any delay or redesign would defeat the new bridge. |
p. 76. We did wrestle
with the question of design, and scale, and, you know, how it would fit into the
community, but were also told, in no uncertain terms, that any delay or redesign
like that would defeat the new bridge.
The Commission has faced on numerous
occasions, Caltrans projects where your conditions of mitigation were argued, or
characterized as conditions that would kill the project, only to find that somehow there
was a way found to make both the project work, and implement mitigation measures. |
| Commissioner Desser |
p. 78. So, I would
like to hear a little bit more about why site-specific design isnt appropriate, or
possible in this case. |
| Douglas Caltrans:
any redesign would kill the project. |
p. 78. I think we
would ask the Caltrans representative to respond. Our staff did have discussions
with them, about a redesign, narrowing of the bridge, and other kinds of issues that deal
with the scale, and we were told that that delay and the costs associated with that would
probably kill the project, and so we relied on that. |
| Desser |
p. 79. And, I guess
just want to point out that either way, we are going to be living with this bridge for a
very, very long time, so if it takes a little bit longer to design the right thing, that
we are going to be living with for the next 40 years, that seems like a small price to pay
up front. |
| Knapp Comment on
scare tactics.
Difficulty of getting more funds |
p. 80. The comment
about tactics, I heard this kind of thing, inn which were using scare tactics, and we were
threatening that we were going to take away the project
What I am saying is that
I cant tell you. I am not the California Transportation Commission. I cannot tell
you, if I go back and say, "We increased the cost of this project by 20 percent
already, from $20 million to $24 million," that was the maximum flexibility we had,
"weve spent $4 million more, and I need $2 million more."
I cannot tell you, and I know how excruciatingly painful it is when we go back and ask
for more money, so I know management of our organization will have to look at it and say,
"Do we want to go back and ask for that additional money?" |
| Tatman Minimum
bridge width |
p. 83. So, what we do
is build the minimum amount of bridge outside, and we build it in pieces. Stage 1, we are
actually building 25.3 feet of bridge. And, that is accounted for, again, in Exhibit 19,
and Vince Taylor mentioned only building 16 feet of bridge width. In fact, that is what we
are building, but that 16 feet is from here to here. What Vince doesnt recognize,
and hasnt recognized throughout our discussions Ive been talking with
Vince since last August. We have had some very nice discussions we also need,
because you have the end of the bridge here, you have to have some k-rail to keep people
from driving into the existing bridge. We are going to have to have some construction
workers on that side of the k-rail walking along, so we have to provide that. We are only
providing one-foot of width. p. 85 What we have developed here is a plan that
doesnt delay traffic at all, and if we can accomplish that, and meet the needs, and
do these enhancements of shoulders, sidewalks, and match the roadway on either side,
that is the plan we were looking for, and a plan that doesnt impact the adjacent
businesses. That is what we have strived for, and that is what we have achieved. |
| Tatman Need for
crane
Vince Taylors contention
Non-response to Taylors contention |
p. 86. On one of the
bridges, the westerly structure, we actually dont build the sidewalk in the first
stage, and the reason is that a crane, in order to dismantle the existing structure
which we start to do in stage 2 only during the day. We end up having to put, for a
short period of time, 2 lanes of traffic on this westerly structure, because the crane
needs to sit on the easterly structure. That is a very limited period of time, in which
that happens. And, I believe Vince Taylor, in his information to you, says he has talked
to some crane operators, and there are actually some cranes that can dismantle this bridge
and dont need to sit up there at all, so therefore we can build less width.
But, I would point out to you that we are concerned also about pedestrian access and
bicycle access during construction, not just the final configuration, but also during
construction, and that is why we are providing a 12-foot lane, and a 4-foot shoulder, and
building one of the sidewalks during the first stage of construction. |
| Desser |
p. 87. And, how long
do you anticipate construction taking under these various scenarios? |
| Tatman Construction
time |
Altogether, about two
years. I think about a year to get these, this first stage done, then probably a month or
two to dismantle the existing structure, and then another like 10 to 12 months to get this
[interruption] center piece built. |
| Commissioner Detloff Question
about acceptability of Caltrans railing design.
Access to Mr. Taylors proposals?
Douglas reply:
Caltrans assertion that new railings would be prohibitive in terms of cost and time.
Accepted that was no feasible alternative, and that is how came up with Condition 6. |
p. 88.
because
I dont see a condition that directly address that, you came to the conclusion that
the design of this particular system that Caltrans is proposing, with some views, would be
acceptable. And, then the width of the bridge was not something that became a point of
study with the Commission. And, I am wondering if you had access to the statements, or the
proposals made by Mr. Taylor, when you were going over.
Well, first of all, relative to the design of the rail, we did discuss with Caltrans
the possibility of a redesign, and they went through what it would take to meet the safety
standards, the crash tests, and all of that, and that that delay, and the costs, would
make it prohibitive.
So, we pretty much felt that there wasnt a feasible alternative to the rail
design, even though we thought that technically there probably could be a more see-through
kind of rail, and that is why we focused on the mitigation of the visual [Detloff:
Exactly] impacts, and that is how we came up with Condition 6. [This is killer!] |
| Detloff
Douglas
Detloff
Douglas
Had to take what Caltrans represented
|
p. 89 So, we really
have come down to what the Coastal Act demands of both the staff and the Commission, and
that is visual resources, and thus Condition No. 6. Thats right.
So, we have taken it down to, we have narrowed our focus as to what our requirements to
meet the Coastal Act are.
That was our view of it, because we felt that we werent expert to redesign and
exactly what you were presented was presented to us, and we pretty much had to take what
they represented. |
| Detloff Existing
railings dont meet current standards.
Douglas |
p. 89. So, we have had
several examples, by public comment, on various railings that are being used around the
state, but I think that the comment made during their presentation by Caltrans that many
of those railings no longer meet state or federal safety requirements. Is that a true
statement? That is what we were told, yes, and we have not reason to question that. |
| Commissioner
McClain-Hill
Douglas
Lack or alternative rail led to Condition 6. |
p. 91 And, with
respect to the visual impacts, am I correct in understanding that it is both the impact of
the new railing, in terms of views as you cross the bridge? and the impact from looking,
views from off of the bridge, looking across.
That is why we felt if they are
not going to be able to redesign the rail, then an off-site mitigation measure that would
enhance public recreational, and visual resources would be an appropriate tradeoff. |
| Commissioner Reilly Is
a seismic safety issue, and dysfunctional to have restriction on trucks going across
bridge |
p. 95.
I am
convinced that there does exist a public safety issue requiring replacement of the current
bridge, and I think Caltrans has made that representation. I have no reason not to believe
that, in terms of the seismic issues. And, I think it would be dysfunctional for what is
still a logging town to have restriction on trucks going across that bridge, and I
dont know how that would work. [Referring back to a comment by Knapp that a retrofit
would require restrictions on trucks.] |
| Reilly Why a $1
million cap on mitigation |
p 96. I think the
amount, probably, the amount that I would support would be $1 million, as opposed to $2
million, as a cap, for a couple of reasons.
And the second thing is that, you know,
in terms of having to go back to the Department of Transportation [I think he means CTC],
somebody else, I think the $1 million is enough to send a message to Caltrans that we are
serious about the view-shed impacts, and it will not jeopardize the bridge project, and so
that is where I am at with it. |
| Commissioner Potter Move
to accept per staff, with $1 million |
p. 98. I am prepared
to move this item, and I am prepared to move per staff, but with a modification as
Commissioner Reilly has suggested, regarding the $1 million versus $2 million cap
|
| Potter
Can build a safe, visual rail
Coast is an attraction to drivers.
Precedent setter: either better rail or off-site mitigation. |
p. 99 Okay I want to
speak to this briefly. And, that is this whole thing revolves around the visual
resources side of the Coastal Act for me. I think this is a precedent-setting project. I
think that we have , as we acknowledged, recognize there will be other bridge projects
here.
And, I have heard this argument that you cant build a safe rail that addresses
the visual issue. I would suspect that, you know, you can. The building contractor in
me says that there is a way to do it. I mean, we can build glass that stops bullets. It
seems to me that there must be a way to address the visual side of this.
And, I cant set any store in the argument that the coast is a distraction, as a
driver. It is an attraction. If we took that argument that you were really being
distracted as you drove down the coast, we would be allowing sound walls down the entire
west side of the coast. So, I dont think we can advocate for, you know, a concrete
pipeline as we go down Highway One.
And, so I think, from that standpoint there is a justification to use this project
as the precedent setter, to go ahead and either construct or design a more appropriate
rail, or have an off-site mitigation that deals with the publics access and visual
side of the Coastal Act. |
| McLain-Hill Public
safety concerns result in impacted views.
Puts a lot of stock in funding issues
Supports Caltrans bridge, opposes fee. |
p. 103. .. well, it is
clear to me that other reviewing bodies have come to the conclusion that this is a public
safety matter, that the bridge, in fact, meets and that there are constraints that
are dictated by public safety concerns, and that those constraints may very well result in
views that are not what we would like them to be.
also, I put a lot of stock in
issues raised with respect to funding, and the fact of the matter is this state is facing
a tremendous crisis with respect to infrastructure investment, and dollars are very hard
to come by. And, you know, a million here, a million there, after awhile it is real
money, and so in my view we really do need to balance that issue, vis-avis what we
gain, by an uncertain mitigation measure
And, so with that, I am supportive of the building, or replacement of this bridge, and
frankly disturbed at the additional imposition of a fee, with respect to Caltrans moving
forward. |
| Commissioner Nava |
p. 104.
I
think, in April of 1997, and it was at that juncture that I made reference to the fact
that all of the views, from whatever vantage point, constitute links of the chain, and
that every time that we interfere, impede, with one of those links of the chain, we
destroy the integrity of this coastline. And, it is just beyond my ability to believe
that Caltrans, with all of the engineers, and all of the degrees, and all of the science,
and all of the materials, and all of its ability to accomplish good work, cant come
up with a bridge design that is esthetically attractive, that maintains the ambience of
the community, that contributes to the glorification of this coast, rather than the
urbanization of it. [Right on, Pedro!] |
| Potter |
p. 113. I just want to
go on the record as quite frankly I am sorry to see this existing bridge go. I am
surprised it didnt have historic designation. I think it is an attractive
structure. The new one looks just a little bit too much like the next millennium for me.
Maybe it is my age, or maybe it is the fact that I am from New England, but we still even
have some old covered bridges around this country that are of incredible historic value.
We just designated three very similar truss designed bridges in Monterey Count as
historic resources, so they would be preserved in perpetuity. So, I am truly sorry to see
this, in the name of progress, and in a desire to move more vehicles more quickly,
creating a concrete structure of this type. |
|