|
| |
|
Grounds for Revocation of Coastal Commission Permit 1‑98‑100 for Replacement of
the
Noyo
Bridge
Vince Taylor
May 31, 1999
|
|
|
Dharma
Cloud Foundation
P.O. Box 37
Caspar, CA 95420
Tel 707 964-6456 Fax 707
964-7520 |
|
|
Grounds
for Revocation of Coastal Commission Permit 1‑98‑100 for Replacement of
the Noyo Bridge
Introduction
On March 12, 1999, the Coastal Commission approved
Application No. 1-98-100 from the California Department of
Transportation (Caltrans) for a permit to build the Noyo Bridge
replacement.
The evidence contained herein shows that all of
the conditions for revocation of this permit are met. Therefore, the
Commission has the authority and duty to revoke this permit.
Grounds for revocation of a Coastal permit are
contained in Title 14, Section 13105 of the California Code of
Regulations (CCR):
Grounds for revocation of
a permit shall be:
(a) Intentional inclusion of inaccurate,
erroneous or incomplete information in connection with a coastal
development permit application, where the commission finds that accurate
and complete information would have caused the commission to require
additional or different conditions on a permit or deny an application;
(b) …
The grounds for revocation under 13105(a)
contains three essential tests:
1. Did the application include inaccurate,
erroneous or incomplete information relative to the permit?
2. Would accurate and complete information have
caused the Commission to require additional or different conditions or
deny the application?
3. If the application included inaccurate,
erroneous or incomplete information, was the inclusion intentional?
For revocation under Section 13105(a), all three
of the above tests need to be met.
This document shows that Caltrans violated Section
13105(a) in two important areas of testimony: 1) the availability of
alternative approved “see-through” railings, and 2) the feasibility of
meeting construction traffic objectives with a narrower bridge.
Caltrans’s testimony in both of these areas meets all three of the tests
of Section 13105(a).
With respect to the first of these three tests,
the evidence presented herein is overwhelming that the application
included erroneous and incomplete information. With respect to the
second test, given the contents and reasoning embedded in the Staff
Report on the Application, as well as the statements of the
Commissioners when voting on the Permit, there can be no doubt that
“accurate and complete information [would] have caused the Commission to
require additional or different conditions or deny the application.”
With respect to the third test, there is no remotely plausible
explanation for the erroneous testimony of Caltrans that does not
involve intentional inclusion.
In
each of two separate areas, bridge railings and bridge width, all of the
tests of Section 13105(a) are met, providing the Commission with the
necessary grounds for revoking Permit 1-98-100.
No Urgent Safety Issue Involved
In considering revocation, the Commission should
be aware that there is not now an urgent safety issue that would weigh
against revocation. In its application for its Coastal Permit, Caltrans
emphasized the need for immediate approval without changes that would
cause a delay in construction. The Noyo Bridge is one of 27 remaining
bridges in the Phase II Seismic Program for bridges. Rick Knapp,
Director of Caltrans District 1, emphasized: “It is critical that the
remaining [bridge] structures [in the Seismic Program] be completed as
soon as humanly possible to protect the safety of the traveling public.”
This urgency weighed heavily in the Commissions approval of the permit.
Now, at the earliest, significant work on the new
bridge will not commence before June 1 of 2000. Caltrans contributed to
the permitting delays that are responsible for the postponement of this
supposedly time-urgent project. After the Coastal Commission approved
the Noyo project contingent upon payment of a $1 million mitigation fee,
Caltrans initiated an internal review of the project that delayed their
request for final approval from the California Transportation Commission
until June, 1999.
In its April announcement of its intention to
accept the $1 million mitigation payment and to proceed with the Noyo
Bridge, Caltrans stated, "Due to delays resulting from the permitting
process, it is not likely that significant work will be accomplished
this year."
A condition of the permit of the National Marine Fisheries is that
pile-driving and cofferdam installation be done between June 1 and
October 15;
therefore meaningful construction cannot occur before June 1, 2000.
Based upon the construction schedule provided by Caltrans to the Coastal
Commission,
Caltrans would have until March 2000 to redesign the bridge and obtain
the necessary permit amendments without creating any new delays.
_____________________________________
|
Presentation of Grounds for Revocation
Section 13105(a) Violations
Permit 1-98-100 meets the conditions for revocation
because of Caltrans’s violation of Section 13105(a). The grounds for
revocation under Title 14 CCR Section 13105(a) contains three essential
tests:
1. Did the application include inaccurate, erroneous
or incomplete information relative to the permit?
2. Would accurate and complete information have
caused the Commission to require additional or different conditions or
deny the application?
3.
If the application included inaccurate, erroneous or incomplete
information, was the inclusion intentional?
Following sections apply these tests separately for
information presented on 1) bridge railings and 2) bridge width.
Errors and Omissions on Bridge Railings
This section presents the evidence on violation of
Section 13105(a) in the area of Caltrans’s testimony on bridge railings.
Test 1: Did the applicant include inaccurate,
erroneous or incomplete information?
Throughout the permit hearings in Fort Bragg and
before the Coastal Commission, Caltrans insisted that the limited
“see-through” railing used in its bridge design was the only one currently
approved.
This assertion is erroneous. At the time Caltrans was making these
statements, there existed a number of existing railing systems that met
federal and state safety requirements and that would better preserve
existing Noyo views.
Figures in Appendix 1 show several railing designs
that are federally approved to at least the crash level of the proposed
railing for the Noyo Bridge.
(Copies of the approval letters from the Federal Highway Administration
for these railings are provided in Appendix 2.)
|
|
·
Figures 1-1 through 1-3 are for “combination railings” that
can be used by themselves on the outer side of bridge sidewalks. They
provide a protection barrier for both pedestrians and automobiles.
·
Figures 1-1 shows a cross-section of the Massachusetts
S3-TL4 Steel Bridge Railing. The spacing of the pickets (Figure 1-2)
would need to be reduced below that shown to meet California standards for
pedestrian railings (maximum 4” spacing), but this change would not
require further testing.
·
Figure 1-3 shows the NETC 4-Bar Sidewalk-Mounted Bridge
Railing, developed by the New England Transportation Consortium (NETC).
As designed and tested, this railing has no vertical pickets, because it
meets the federal standards for pedestrian railings of a maximum 6”
opening between members. Because California requires maximum 4” spacing
on pedestrian railings, it would not be acceptable in California unless
vertical pickets were added to it.
·
Figure 1-4 shows the Wyoming 2-Tube traffic railing. It is
only one of many approved traffic railings, but stands out because of its
low visual obstruction. This railing is of particular interest for the
Noyo Bridge because it allows a railing solution that offers both
increased safety for pedestrians and maximum views for motorists.
Traffic railings, such as
the Wyoming Railing provide protection for vehicles but do not meet
standards for pedestrian protection. However, federal and California
bridge standards allow use of traffic railings to separate pedestrians
from vehicle traffic
on bridges, allowing use of a lighter-weight pedestrian railing on the
outside of the bridge. Because pedestrian railings can be of much lighter
material than combination railing, they allow for much greater
visibility. A picket-type railing, which has most members oriented
vertically, provides almost unimpeded visibility for motorists because
vertical elements are essentially invisible from moving vehicles.
Figure 1-5
shows the cross section of the Redwood Creek Bridge in Humboldt County,
California. This bridge uses a combination railing to separate the
sidewalk from traffic and uses a pedestrian/bicycle railing on the
outside. Figure 1-6 shows the picket-style pedestrian railing for this
bridge. As noted above, this type of railing provides essentially
unimpeded views to pedestrians.
|
|
This bridge was designed in 1996 and meets current
California safety regulations.
The railing system used on the Redwood Creek
Bridge provides a starting point for designing an environmentally
outstanding railing for the Noyo Bridge. The Type 27 Concrete Railing
used on the Redwood Creek Bridge as a traffic barrier would be replaced
with the Wyoming Railing. The outer pedestrian railing would be similar
to the one used on the Redwood Creek Bridge, perhaps modified to provide
more architectural interest but retaining the vertical-element design.
The result would be a railing system that would provide almost unimpeded
views for motorists. The railing system would meet current federal and
state safety standards.
The evidence confirms that the first essential test
for revocation is met.
Test 2: Would accurate and complete
information have affected the conditions or the approval of the permit?
A major factor in the acceptance by the Coastal
Commission of the proposed bridge design was Caltrans insistence that no
“see-through” railing design other than the one proposed met current
safety standards:
“… this [proposed] design
does not fully protect views as required by Section 30251 [of the Coastal
Act]. Alternative designs that provides for increased visibility
certainly exist. Many railings on other roads and bridges provide for more
visibility … However, Caltrans points out that its safety standards have
changed, and the ‘see-through’ barrier incorporated in the project is
the only one currently approved. Caltrans estimates that the design,
crash testing and approval process for an improved ‘see-through’ barrier
could take from 2 to 4 years.”
The Staff Report further states that "Caltrans has taken the position that
such a delay is not acceptable (Exhibit 18)." [Emphasis added.]
Based on these statements, the Staff Report
concluded, "Thus, no available feasible alternative railing design
currently exists that meets the necessary safety criteria."
This conclusion was instrumental in the staff's recommendation to the
Commission to accept the Caltrans design and to compensate for the loss of
views by attaching Special Condition No. 6, which provides for Caltrans to
pay a mitigation fee.
The evidence confirms that the second essential test
for revocation is met.
Test 3: Was the
inaccurate, erroneous or incomplete information included intentionally?
|
|
In attempting to determine whether or not errors and
omissions of Caltrans were intentional, it is necessary to consider two
statements put forth simultaneously by Caltrans in their testimony on
their application.
Statement 1: Federally approved railings are
acceptable to Caltrans.
The Staff Report on the application for the Noyo
Bridge permit states:
Caltrans’ policy is that
“all bridge railings must be crashworthy by testing following AASHTO
[American Association of State Highway Transportation Officials]
guidelines” and be accepted by the Federal Highway Administration (FWHA).”
Eldon Davisson, Chief, Office of Structural Design,
Caltrans, confirmed that the above quote accurately represents Caltrans
policy.
Statement 2:
The “see-through” barrier incorporated in the project is the only one
currently approved.
Rick Knapp, Director of Caltrans District 1, in
which Fort Bragg is located, stated in a letter to the Mayor of Fort
Bragg:
At that meeting [held on
September 16, 1998], Caltrans committed to include a see-through railing
if we could get an approved, safety-tested design before construction of
the project. Subsequent to the meeting, a design was safety-tested and
approved by Caltrans and the Federal Highway Administration which has
“see-through’ component. While some are not happy with the proposed
railing, I must emphasize that we do not have the luxury to provide
railings that do not meet State and Federal safety standards.
The Staff Report on the permit application states,
“However, Caltrans points out … the ‘see-through’ barrier incorporated in
the project is the only one currently approved. [Emphasis added.]
Statements 1 and 2 are not compatible with
facts that Caltrans knew or should have known.
|
|
First, Caltrans testified that federally railings
approved could be used on the proposed Fort Bragg Bridge (Position 1).
Second, Caltrans professionals insisted that there were no approved
railings other that the one proposed (Position 2). These positions
together imply that Caltrans had done a thorough search for federally
approved “see-through” railings and had come up empty handed. Certainly,
given the amount of controversy over the proposed railing, any reasonable
person would expect Caltrans to have done the thorough search implied by
its unconditional statement that there were no other approved railings.
As has been shown herein, there are a number of
federally approved railing designs in addition to the one proposed. Is
it possible that Caltrans professionals could have made a thorough search
but not found the approved alternative railings? No, it does not seem
possible. It took me, who had no prior knowledge of the Federal
Highway Administration, only a few phone calls to determine that there
were two federally approved see-through pedestrian/traffic railings
(combination railings) and numerous approved traffic railings that can be
used as barriers between sidewalk and traffic lanes (traffic railings).
Caltrans professionals are much better connected to the bridge safety
section of the Federal Highway Administration than I.
Another possibility is that the Caltrans
professionals on the Noyo Bridge project did not know that railings
approved by the Federal Highway Administration are generally acceptable to
the state, even though this is the Caltrans policy. But, this is not a
realistic possibility, because the Structures Division of the Engineering
Service Center of Caltrans was the source within Caltrans for its proposed
“see-through” railing and also the source of the confirmation that
federally approved railings were acceptable to the state.
There are only two realistic possibilities:
·
Caltrans professionals knew that there were approved
alternative railings but intentionally omitted mention of them from their
testimony, or
·
Caltrans professionals did not search for federally approved
alternative railings, but intentionally implied that they had done so and
found no other approved railings.
Regardless
of which possibility is correct is irrelevant to determining whether there
was “intentional inclusion of inaccurate, erroneous or incomplete
|
|
information” by Caltrans, because both possibilities
involve intentional misrepresentation by Caltrans.
The evidence confirms that the third essential test
for revocation is met.
All tests for revocation are met
In the area of Caltrans’s information supplied to
the Commission on bridge railings, all of the tests of Section 13105(a)
are met, providing the Commission with the necessary grounds for revoking
Permit 1-98-100.
Errors and Omissions on Bridge Width
This section presents the evidence on violation of
Section 13105(a) in the area of Caltrans’s testimony on the minimum
feasible bridge width.
Background
Although railing designs for the Noyo Bridge have
received the most attention in regulatory hearings, the excessive width of
the proposed design contributes equally to its destruction of coastal
values. The bridge is described as a “four-lane bridge”, but it has not
just four traffic lanes and two sidewalks, but an unused 12’ center median
and two eight foot shoulders. Including sidewalks, the proposed bridge is
87 feet wide, wider than the Golden Gate Bridge,
almost completely filling its right of way and coming within 10 feet of a
restaurant and motel on the seaward side of the bridge.
The excessive width of the bridge directly violates
the Fort Bragg LCP Scenic Corridor Combining Zone regulations, which
requires that structures in this zone contribute to the “character and
image of the city as a place of beauty, spaciousness and balance.”
The excessive width, as well as the Caltrans railing design, makes
impossible the preservation of existing views. The shoulders plus
pedestrian lanes total 13.5 feet, compared to 4.5 feet on the current
bridge; thus drivers are moved 8.5 feet further away from the edge and
have a significantly shallower downward angle of view.
Maintaining the present downward angle of view for motorists is critically
important to maintaining the harbor views. The boundary between the water
and buildings in the harbor is relatively close to the bridge. To see the
pilings of the piers requires the present downward angle. On the
proposed bridge, drivers would be unable to see the waters of the harbor
even if there were no railing at all.
|
|
Decreasing the width of the bridge is essential to
maintaining the present coastal views.
Test 1: Did the
applicant include inaccurate, erroneous or incomplete information?
Caltrans plans to construct the Noyo Bridge in two
stages. In Stage 1, two outlying bridge sections will be built along side
the existing bridge. When they are completed, the existing bridge will be
dismantled and Stage 2 construction will fill in the gap between the Stage
1 sections, creating a single, unified bridge span.
Caltrans has insisted throughout all permit hearings
that the constructed bridge is the minimum width that could be constructed
“without accepting major impacts to motorized and/or non-motorized traffic
during construction.”
Therefore, it has not presented any alternative, narrower designs.
Caltrans explains its position:
The easterly [Stage 1]
bridge section will be 25.3’ wide; …This width is necessary for
construction safety of traffic, non-motorized traffic, and construction
workers.
The westerly [Stage 1]
bridge section will match the easterly bridge section and carry one lane
of traffic also, but with one exception. It will not have a sidewalk
built initially. The additional width will be used to accommodate two
lanes of traffic during a limited period of time when a large piece of
equipment will need to sit on the easterly bridge section to begin
dismantling the existing bridge. During this time, the easterly bridge
will not be available to traffic during the day. The westerly bridge
section will be 25.3’ wide…
To provide less than these
temporary construction widths would mean that either some or all of the
pedestrian, disabled, bicycle, and motorized traffic would be subject to
major delays or would be unable to get across the bridge altogether during
construction.
Bridge
width not justified by need to maintain two-way traffic.
Caltrans
proposes to build lanes on each side of the existing bridge equal to 24.3
feet during Stage 1. But, only a 18.7’ lane would be needed to provide an
11-foot traffic lane, a 1-foot-wide railing, a temporary 4-foot pedestrian
lane, a 2-foot edge barrier, and 0.7 foot of overhang. Omitting the
pedestrian lane on one side in Stage 1, as Caltrans proposes to do, the
second Stage-1 bridge
|
|
section could be 14.7’ wide. The total width of the
bridge would then be 69.4 feet, rather than the 87-foot width of the
bridge proposed by Caltrans.
Caltrans dismantling plan determines bridge
width. The critical factor that drives the width of the proposed
bridge is Caltrans’s assertion that “a large piece of equipment will need
to sit on the easterly bridge section to begin dismantling the existing
bridge.” Closing the east section creates the need to build the west
section sufficiently wide to carry two-way traffic in order not to create
“major delays.” The proposed west section width of 25.3’ is just
sufficient to allow two 11’ traffic lanes (0.8 feet less than a “standard”
lane), even omitting a sidewalk.
Caltrans omitted consideration of alternative
ways to dismantle bridge. If it were true, as Caltrans asserts, that a
“large piece of equipment” (a crane) were needed on the east section, the
proposed bridge would be the minimum width that would allow staged
construction and avoid extended one-way traffic. However, what Caltrans
omitted from its testimony was that the proposed dismantling plan is
merely conceptual.
The dismantling scenario described is not an essential aspect of the
staged construction plan that Caltrans prefers.
There are many different possible ways to dismantle
the bridge, not all of which require a crane to be located on one of the
new bridge sections. I discussed alternative dismantling plans with two
crane-rental companies and with Caltrans personnel. Some points that
emerged from these conversations and Caltrans documents:
·
Caltrans’s current dismantling scenario envisions that a
section of approximately 100’ would be cut from the center of the bridge
and lowered as a single piece without the use of cranes. “Draw works”
would be attached to the section to be lowered. The lowering cables would
be attached to the remaining sections.
The center section of the bridge could be lowered to the temporary trestle
to be built as part of construction and then barged to land; the entire
operation should not take longer than one day.
·
“At least two” large cranes (200-250 tons) are envisioned by
Caltrans as being located below the bridge, on temporary trestles, during
bridge construction and dismantling.
|
|
·
The size of the crane envisioned by Caltrans as being placed
on the new east section would be restricted by the 21’ clear width
(including the sidewalk) of the section. Only “a small hydro-type crane
could fit in 21 feet.”
·
Cranes could operate from below the bridge or from the ends
of the bridge as substitutes for the crane envisioned by Caltrans as being
placed on the new bridge section. There is no question of feasibility,
only of cost.
·
With respect to the cost of alternative dismantling
approaches, note that narrowing the bridge by 15 feet, an entirely
feasible amount, would save $3 million in construction costs – far more
than the possible additional cost of a dismantling alternative that avoids
use of a new bridge section.
What emerges clearly is that there exist
feasible alternatives for dismantling the bridge that do not require
long-term closure of one of the new sections of the bridge.
Caltrans omitted any discussion or analysis of these alternatives in
its testimony. By omitting discussion of dismantling alternatives,
Caltrans precluded consideration of narrower-bridge designs.
The Coastal Commission Staff Report also omits any
discussion of a narrower-bridge alternative. When queried about why this
omission occurred, the Commission staff person in charge of preparing the
report said that Caltrans rejected all suggestions for a narrower bridge.
The evidence confirms that Caltrans presentation of
information was incomplete; thus the first essential test for revocation
is met.
Test 2: Would accurate and complete
information have affected the conditions or the approval of the permit?
Protection of the existing scenic views is a major
objective of the Coastal Act and was a major concern expressed in the
Staff Report on the Appeal and Application:
The area
framed by the Noyo Rive bluffs in and around Noyo Harbor, the mouth of the
river and Noyo Bay is an area of exception visual interest and scenic
qualities. This fact is fully reflected in the Fort Bragg
|
|
LCP … it calls for the
protection of these scenic values and views. … The proposed bridge would
introduce a significantly enlarged, urban-type structure into the views of
this scenic corridor area. The proposed bridge would be highly visible
from visitor destinations … and would affect views to and from the bluff,
the scenic setting at the mouth of the Noyo, and the ocean.
…
The particular
configuration and design of the existing bridge, especially the high
visibility afforded by its current railings, afford generous views for
motorists from the bridge itself to and along the ocean and the scenic
coastal area of Noyo Harbor and the Noyo River. The bridge is in fact one
of the few places in Fort Bragg where the ocean is visible from Highway
1. The bridge is also a highly visible feature of the coast views
afforded from visitor destination points and recreational area in and
around Noyo River. The prominence of the bridge makes the bridge one of
the most significant elements defining the character of the area.
The excessive width of the proposed bridge makes it
fundamentally incompatible with the requirement of the Coastal Act “to
protect the scenic and visual qualities of coastal areas.” The present
bridge is 34 feet wide. Including sidewalks, the proposed bridge is 87
feet wide, wider than the Golden Gate Bridge,
almost completely filling its right of way and coming within 10 feet of a
restaurant and motel on the seaward side of the bridge.
Detracts from spaciousness, balance, and
appearance. Because of its excessive width, the proposed bridge
cannot possibly conform to Fort Bragg LCP Scenic Corridor Combining Zone,
Section 18.58.050(C), which includes the following requirements (emphasis
added):
·
The structure shall be so designed that it in general
contributes to the character and image of the city as a place beauty,
spaciousness and balance.
·
The exterior design and appearance of the structure is not
of a quality or scale so as to cause the nature of the neighborhood
to materially depreciate in appearance and value.
Rather than
contributing to a sense of spaciousness and balance, the bridge
would crowd up against the existing buildings and destroy the balance
between open spaces and structures, materially
|
|
depreciating the appearance of the neighborhood. All of this would
occur in an area of exceptionally important coastal resources.
Makes impossible the preservation of valuable coastal views. The
proposed bridge would place drivers about 20 feet from the edge of the
bridge, nine feet further than they are on the present bridge. Thus, on
the proposed bridge, drivers would have a significantly shallower downward
angle of view.
The staff report recognizes the decreased downward angle of view,
but does not recognize that maintaining the downward angle of view is
critically important to maintaining the harbor views. The boundary
between the water and buildings in the harbor is relatively close to the
bridge. To see the pilings of the piers requires the present downward
angle. On the proposed bridge, drivers would be unable to see the
waters of the harbor even if there were no railing at all.
In my testimony before the Coastal Commission on the Noyo-Bridge permit, I
showed how a narrower bridge, combined with a different railing approach,
could completely preserve existing views from the bridge.
A narrower bridge, thus, would contribute significantly to preserving
important coastal resources. Had Caltrans presented the Commission with
the option of a narrower bridge, the Commission seems likely to have
required different conditions or to have denied a permit for the proposed
bridge.
The evidence confirms that the second essential test for revocation is
met.
Test 3: Was the inaccurate, erroneous or incomplete information
included intentionally?
I discussed
the subject of bridge width with the Caltrans Project Leader for the Noyo
Bridge, Karen Tatman, several times, beginning in Fall of 1998. I argued
for a narrower bridge in my testimony before the Fort Bragg Planning
Commission on December 9, 1998.
In my testimony to the Coastal Commission, which was known to Ms. Tatman
prior to the Coastal Commission hearing, was the assertion by John
Anderson of Bragg Crane that placement of
|
a crane on the bridge was not necessary for dismantlement.
The Commission staff also inquired about the possibility of a narrower
bridge prior to the hearing.
Therefore, the Caltrans project team was aware that bridge width was an
issue.
The project team was certainly in communication with the Caltrans Office
of Structure Construction, a member of which stated to me that there
were “surely” dismantling alternatives that would not require placement
of a crane on one of the new bridge sections.
What is clear from talking with a number of engineers and dismantling
professionals is that there is always a variety of ways available to do
a given dismantling project.
What seems apparent from conversations with the Caltrans Project Manager
and the record is that Caltrans was aware that there very well might be
dismantling alternatives compatible with a narrower bridge but chose not
to explore them and not to present them to the Commission.
Because consideration of dismantling alternatives was essential to
consideration of narrower-bridge alternatives, Caltrans intentional
omission of dismantling alternatives precluded consideration of
narrower-bridge alternatives.
The evidence confirms that the third essential
test for revocation is met.
All tests for revocation are met
In the area of Caltrans’s information supplied to the Commission on
bridge width, all of the tests of Section 13105(a) are met, providing
the Commission with the necessary grounds for revoking Permit 1-98-100.
Conclusion
In both the areas of bridge railings and bridge
width, the information supplied to the Coastal Commission by Caltrans
meets the three tests required to establish a Section 13105(a)
violation. A violation in either area is sufficient grounds for
revocation of Permit 1-98-100.

|
Appendix 1
Selected Federally Approved Bridge Railings
[To be supplied]
|
|
Appendix 2
Federal Approval Letters for Selected
Bridge Railings
[To be supplied]
|
|